Example report · not a live site
Near Keighley, West Yorkshire
Yorkshire network area · read 5 Oct 2026 · point 53.860, -1.896
Grid verdict
Promising for power
Ranked 26th of the screened cells in the Yorkshire network area. No flags raised.
- Nearest primary
- 0.9km
- Published headroom
- 20.2MVA
- Time to power, 5 MW
- 17 to 28months
- Route to 10 MW+
- Yes
Substation proximity and headroom
Nearest primary
Keighley Direct, 11 kV, 0.9 km away
PowerFirst grid analysis, 5 Oct 2026
Spare demand capacity
20.2 MVA published at that primary
PowerFirst grid analysis, 5 Oct 2026
Already accepted there
1.8 MVA of large demand
PowerFirst grid analysis, 5 Oct 2026
Higher-voltage sites
Keighley 132 kV substation 0.9 km; South Street 33 kV 1.1 km; a transmission line 0.1 km
PowerFirst grid analysis, 5 Oct 2026
Voltage level and the route to 10 MW+
First phase
5 MW of IT needs about 6.8 MVA, so a 33 kV connection is assumed
PowerFirst time-to-power model, 5 Oct 2026
Route to 10 MW+
Yes. 20.2 MVA covers 10 MW of IT (about 13.7 MVA)
PowerFirst time-to-power model, 5 Oct 2026
Time to power, 5 MW
17 to 28 months (P10 to P90), middle 22.5. Confidence high
Application about 3 months, study 1 to 9, works 7 to 19, energise 1 to 2.
PowerFirst time-to-power model, 5 Oct 2026
Quote standard
50 to 65 working days for an EHV demand quote
PowerFirst grid analysis, Mar 2026
Bridge power
A mapped gas pipeline 2.8 km away. Engine fuel costs about half the grid price, fuel only
PowerFirst market analysis, Jun 2026
Fibre and latency
Nearest mapped data centre
16.8 km
A proxy for nearby fibre. The full report confirms routes and latency with carriers.
PowerFirst market analysis, 5 Oct 2026
Tenant demand nearby
Mapped data centres
7 within 25 km, 17 within 50 km, 36 within 100 km
PowerFirst market analysis, 5 Oct 2026
Investor and capital activity nearby
Data centre lending
2 new registered charges in the last 12 months over data centre operators with sites within 100 km
Operators with sites 37 km and 86 km away; charges dated 17 Mar 2026 and 30 Dec 2025.
PowerFirst market analysis, 5 Oct 2026
Planning and policy signals
Designations
Outside green belt and SSSI
PowerFirst planning and policy analysis, 5 Oct 2026
Air quality
Outside any Air Quality Management Area
PowerFirst planning and policy analysis, 5 Oct 2026
Local opposition or moratoria
None found
PowerFirst news watch, 5 Oct 2026
Flood and water
Flood
Point check passed: outside mapped flood zones
PowerFirst planning and policy analysis, 5 Oct 2026
Water
Not screened here. The full report asks the water company
PowerFirst site screen, 5 Oct 2026
Indicative land value or lease range
Range
Given for your plot only
A real report gives a range for your plot, built from cited sales and lease evidence near you. This example covers an area, not a plot, so it shows no figure.
PowerFirst site screen, 5 Oct 2026